MAAS Aviation have further developed their relationship with Airbus. In 2014 MRO Facilities International assisted them to win the bid to provide a single aisle paint shop as part of the Airbus US FAL ( Final Assemble line) in Mobile, Alabama.
The construction started in March 2014, and was completed by the end of June 2015. JESCO were selected as the main contractors for the project, With JESCO M&E as the Mechanical and electrical contractor.
The facility has a fully air-conditioned and humidity controlled vertical down flow paint extract ventilation system.
The building will conform to US regulation including NFPA 409 and OSHA requirements.
The cost is of the order of $10million.